Plumb Beach Bike Path To Be Repaired… But Not In Time For Summer Cycling
It looks like we’ll be going our fourth consecutive summer without the Plumb Beach bike path, which was destroyed by a nor’easter in November 2009.
But, if all goes according to plan, cyclists will finally be able to enjoy uninterrupted rides from Emmons Avenue to the larger Jamaica Bay Greenway by fall, as the Parks Department has confirmed that they anticipate construction to begin this August.
“We are concurrently in the process of registering funds for the project, and awaiting approval from DEC. The scope of work includes the reconstruction of eroded portions of the asphalt bike path. The two segments we will address comprise a total of approximately 450 linear feet. We anticipate construction to begin at the end of August 2014,” wrote Parks spokesperson Meghan Lalor in an e-mail to Sheepshead Bites.
To strip the bureaucratic speak, what it basically means is that money is in the pot for the construction, and they’re working through the red tape to ensure all relevant agencies are on board.
Lalor noted that it’s too soon to say whether the project would be done in-house by the Parks Department, or bid out to a contractor (which could potentially delay the process).
It’s been a long road in getting a mere 450 feet of asphalt put down. It was destroyed when Hurricane Ida – by then a nor-easter – made landfall in 2009. The waves not only battered the bike path, but diminished several feet of sand from the beach and exposed the Belt Parkway to flooding (a problem that was addressed only mere days before Superstorm Sandy).
In 2010, the city pulled a fake-out, getting the strip ready for repaving… and then calling it quits and vanishing.
Relief seemed to be in sight in 2012, when $9 million in improvements to the area were unveiled, including long-term fixes at Plumb Beach and the development of Brigham Street Park. Then-Councilman Lew Fidler told Sheepshead Bites that some of those funds would cover the bike path repair, yet the Parks Department later said that, in fact, none of the allocated funds would be put to the reconstruction.
Finally, last summer, Fidler informed Sheepshead Bites that he had allocated $450,000 in the Fiscal Year 2014 city budget specifically for shore up the bike path and laying new asphalt. While most Parks projects take three to four years from funding to completion, Fidler predicted – correctly, it seems – that this project would move more quickly.