Ave U, Gravesend Stations Delayed: No Surprises
Just one month shy of the first-year anniversary of construction at the Avenue U and Gravesend Neck Road train stations, the sites reek of the failures soon to ail the rest of the line.
For those who don’t take the train often, above is a photo of the Avenue U train station taken from the platform. They began putting up new frames that will hold the walls here and at the Neck Road train station earlier this week. Work began on the two stations in December 2008, and the MTA said that they finish the Coney Island-bound sides by the end of 2009. Then they’d switch to the Manhattan-bound side, polishing off the project in 2010.
Well, that was the original plan. The MTA changed the Brighton Line Rehabilitation website to reflect the fact that these sites ain’t gettin’ done on time. The tentative date for completion for the Coney Island-bound side is now “Early 2010”, and the full project will be done in “Early 2011.”
If you haven’t noticed, this is the same “Two year plan” that has been extended to the rest of the local stops between Newkirk Avenue and Kings Highway. One year work on the Coney Island side, then one year on the Manhattan side. Gee, you think they’ll honor those schedules?
By the by, for anyone keeping track, the MTA has not yet responded to our leaders’ requests for more information. Politicians and organizers for the area met with MTA officials a month ago to ask for alternatives to the work and guarantees of the timetable. MTA told them they would be in touch in a few days after they had gathered relevant data. Apparently there are delays on that, too.