Notice: Belt Pkwy Lane Closures Near Guider Ave Bridge
On June 28, installation of the new steel superstructure for the East 8th Street / Guider Avenue Belt Parkway overpass will commence at the south end. Night time lane closures will begin on July 5 as the steel installation progresses northward over the South Service road and Belt Parkway. The nightly closures are expected to occur over a period of about three weeks. Night time lane closures on the Belt Parkway will continue, with up to two lanes being closed between 10:00 p.m. and 6:00 a.m. in either or both directions.
Belt Parkway Lane Closures
Eastbound and/or Westbound between Knapp Street and Shell Road
Sunday night through Friday morning:
10 p.m. to 1 a.m. – 1 lane closed
1 a.m. to 5 a.m. – 2 lanes closed**
**On some nights, there will be an all-lane closure at 15-minute intervals. Queued traffic must dissipate completely before another all-lane closure is permitted.
Friday night to Saturday morning:
11 p.m. to 1 a.m. – 1 lane closed
1 a.m. to 6 a.m. – 2 lanes closed