> ## Content Index
> Fetch the complete content index at: https://bklyner.com/llms.txt
> Use this file to discover other available public pages before exploring further.

# Fort Greene Park Willoughby Entrance Construction Update: We’re Halfway There
- URL: https://bklyner.com/fort-greene-park-willoughby-entrance-construction-update-were-halfway-there-fortgreene/
- Published: 2015-05-15T16:30:52.000Z
- Updated: 2015-05-15T17:18:05.000Z
- Author: Heather Chin
- Tags: fort greene park conservancy, Willoughby Avenue entrance, #API-Imported

![Image via Fort Greene Park Conservancy.](/content/images/wp-content/uploads/2015/05/fort-greene-park-construction-map_may2015.jpg)

Image via Fort Greene Park Conservancy.

A message from the [Fort Greene Park Conservancy](http://www.fortgreenepark.org/?ref=bklyner.com) has announced that reconstruction of the Willoughby Avenue Entrance “is 50 percent complete” and is scheduled to be done — ready for reopening — by November/December 2015, according to the NYC Parks Capital Projects [Tracker](http://unitdesign.us8.list-manage.com/track/click?u=b81cb10c8ac5cb9c9bf930d52&id=8970ec06ef&e=67c93e98c5&ref=bklyner.com).

A checklist of things completed in the $1.4 million project are as follows:

- New sewers, pipes, and catch basins have been installed.
- The contractor is currently laying granite curb edging.
- The Willoughby Avenue sidewalk, in front of the construction entrance, will be fenced off temporarily for reconstruction starting this week. Please use the east side of Willoughby Avenue as an alternative.

Additional federal funding will also be helping to improve sidewalks along Washington Park, said the Conservancy.